022 Land at Honeypot Lane, Brentwood
Representation ID: 15898
Received: 12/05/2016
Respondent: Barwood Land and Estates Ltd
Agent: Chilmark Consulting Limited
Support the inclusion of Land at Honeypot Lane because the site is:
- readily deliverable now and can therefore contribute to the five-year housing land supply
- close proximity between jobs, homes and open spaces
- accessible by public transport, on foot and by bicycle
- offers a development opportunity that will support and reflect the distinctive character of Brentwood and the contribution of the wider Green Belt to Brentwood's quality of life, biodiversity and environment
- opportunity to refine and re-align the Green Belt boundary.
See attached.
Support
Draft Local Plan
Appendix 2 - Proposed Housing Delivery
Representation ID: 16318
Received: 12/05/2016
Respondent: Barwood Land and Estates Ltd
Agent: Chilmark Consulting Limited
Support the inclusion of Land at Honeypot Lane.
Appendix 2 identifies Honeypot Lane as providing a total of 250 dwellings in the first five years of the plan period and BLEL welcomes this identification of the opportunity to deliver housing on the site early in the plan period.
BLEL suggests that there should be some flexibility to the housing delivery phasing shown in the Draft Local Plan at Appendix 2 and 3 given the need to achieve detailed planning permission for the site in 2017 in order to allow time for the first phase of development to be completed in 2018.
See attached.
Support
Draft Local Plan
Appendix 3 - Housing Trajectory
Representation ID: 16319
Received: 12/05/2016
Respondent: Barwood Land and Estates Ltd
Agent: Chilmark Consulting Limited
Confirm the ability to bring forward new housing on the Honeypot Lane site in the five-year period.
BLEL suggests that there should be some flexibility to the housing delivery phasing shown in the Draft Local Plan at Appendix 2 and 3 given the need to achieve detailed planning permission for the site in 2017 in order to allow time for the first phase of development to be completed in 2018.
See attached.