MM15

Showing comments and forms 1 to 2 of 2

Object

Schedule of Potential Main Modifications

Representation ID: 29872

Received: 25/11/2021

Respondent: Land North of Shenfield Developer Group

Number of people: 4

Agent: Barton Willmore

Legally compliant? Not specified

Sound? No

Representation Summary:

As currently drafted, a developer (of a scheme over 500 homes) is forced to consider a decentralised system before any other alternatives. It does not allow a developer to demonstrate that alternative solutions could deliver the overall aim of the policy. Object to the wording of B(ii and iii) which should be rewritten to to allow a developer to demonstrate that an appropriate strategy has been included in the development.
Policy places the burden of proof on the developer when it is right for the Council to have first demonstrated the deliverability of such technology.

Full text:

See attached

Attachments:

Object

Schedule of Potential Main Modifications

Representation ID: 29879

Received: 26/11/2021

Respondent: Stonebond Properties Ltd

Agent: Phase 2 Planning and Development Ltd

Legally compliant? Not specified

Sound? No

Representation Summary:

Objects to modifications to part B of the policy which seeks to group sites together that are capable of delivering more than 500 units and requires them to include energy masterplans that incorporate a decentralised energy infrastructure. Concerned that these modifications proposed will have significant impacts on scheme viability and deliverability, which has not been considered within the Local Plan evidence base.

Full text:

See attached