POLICY R24: LAND OFF STOCKS LANE

Showing comments and forms 1 to 5 of 5

Object

Brentwood Local Plan 2016 - 2033 (Pre-Submission, Regulation 19)

Representation ID: 22575

Received: 19/03/2019

Respondent: Essex Wildlife Trust

Legally compliant? Yes

Sound? No

Duty to co-operate? Yes

Representation Summary:

Policy wording omits to mention the need to avoid impacts on Bre57 Furze Wood LoWS.

Policy wording lacks a commitment to deliver biodiversity net gain.

Change suggested by respondent:

b. provision for "multifunctional" publicly accessible open space to deliver a measurable net gain in biodiversity;

c. protect and enhance Bre57 Furze Wood LoWS

Full text:

Policy wording omits to mention the need to avoid impacts on Bre57 Furze Wood LoWS.

Policy wording lacks a commitment to deliver biodiversity net gain.

Support

Brentwood Local Plan 2016 - 2033 (Pre-Submission, Regulation 19)

Representation ID: 23228

Received: 19/03/2019

Respondent: Thames Water

Representation Summary:

On the information available to date we do not envisage infrastructure concern regarding wastewater network or wastewater treatment infrastructure capability in relation to this sites. Please note that the above comments relate to the sewerage network within the Thames Water supply area only. It is recommended that Anglian Water are also consulted for their comments in relation to this development proposal. Drainage hierarchy to be followed in addressing surface water.

Full text:

Dear Sir/Madam,
Thank you for consulting Thames Water on the above document. Thames Water is the statutory sewerage undertaker for part of the Borough and is hence a "specific consultation body" in accordance with the Town & Country Planning (Local Development) Regulations 2012.
Planning Policies
Thames Water support the proposed policies within the Pre-submission Local Plan. Notwithstanding this it is suggested that minor modifications are made to the text within Policies SP01 and SP04 in order to ensure that the policies are effective in relation to ensuring development is delivered alongside any necessary sewerage infrastructure reinforcement works required to support it. The proposed modifications are set out in the attached response forms. In relation to Policy NE02 the requirement for engagement with sewerage providers is welcomed. To assist with promoting early engagement it would be beneficial if a link to Thames Waters pre-application service could be provided on the Councils website. Details regarding Thames Waters pre-application service can be found at: www.thameswater.co.uk/preplanning

Site Specific Comments
We have undertaken a high level review of the proposed site allocations within the Thames Water catchment and have appended comments in relation to wastewater infrastructure issues for these sites in table below.
R04 & R05 - Ford Headquarters and Council Depot, Warley: The wastewater network capacity in this area may be unable to support the demand anticipated from this development. Local upgrades to the existing drainage infrastructure may be required to ensure sufficient capacity is brought forward ahead of the development. Where there is a potential wastewater network capacity constraint, the developer should liaise with Thames Water to determine whether a detailed drainage strategy informing what infrastructure is required, where, when and
how it will be delivered is required. The detailed drainage strategy should be submitted with the planning application. R06 - Land off Nags Head Lane, Brentwood The wastewater network capacity in this area may be unable to support the demand
anticipated from this development. Local upgrades to the existing drainage infrastructure may be required to ensure sufficient capacity is brought forward ahead of the development. Where there is a potential wastewater network capacity constraint, the developer should liaise with Thames Water to determine whether a detailed drainage strategy informing what infrastructure is required, where, when and how it will be delivered is required. The detailed drainage strategy should be submitted with the planning application.
R07 - Sow & Grow Nursery, Ongar Road, Pilgrims Hatch
On the information available to date we do not envisage infrastructure concerns regarding wastewater network or wastewater treatment infrastructure capability in relation to this site/s. It is recommended that the Developer and the Local Planning Authority liaise with Thames Water at the earliest opportunity to advise of the developments phasing. Please contact Thames Water Development Planning, either by email Devcon.team@thameswater.co.uk tel: 02035779998 or in writing Thames Water Utilities Ltd, Maple Lodge STW, Denham Way, Rickmansworth, Hertfordshire, WD3 9SQ
R08 - Land adjacent to Camel, Mascalls Lane, Warley
On the information available to date we do not envisage infrastructure concerns regarding wastewater network or wastewater treatment infrastructure capability in relation to this site/s. It is recommended that the Developer and the Local Planning Authority liaise with Thames Water at the earliest opportunity to advise of the developments phasing. Please contact Thames Water Development Planning, either by email Devcon.team@thameswater.co.uk tel: 02035779998 or in writing Thames Water Utilities Ltd, Maple Lodge STW, Denham Way, Rickmansworth, Hertfordshire, WD3 9SQ. We do not envisage network infrastructure concerns regarding wastewater infrastructure capability in relation to this site on a basis that it won't be any surface water connection into a public foul sewer system. Connection of surface water into a public foul sewer system reduces sewer capacity and has the potential to cause flooding to existing customers. Drainage hierarchy to be followed in addressing surface water.
R09 - Land west of Warley Hill, Pastoral Way, Warley
On the information available to date we do not envisage infrastructure concerns regarding wastewater network or wastewater treatment infrastructure capability in relation to this site/s. It is recommended that the Developer and the Local Planning Authority liaise with Thames Water at the earliest opportunity to advise of the developments phasing. Please contact Thames Water Development Planning, either by email Devcon.team@thameswater.co.uk tel: 02035779998 or in writing Thames Water Utilities Ltd, Maple Lodge STW, Denham Way, Rickmansworth, Hertfordshire, WD3 9SQ
Drainage hierarchy to be followed in addressing surface water. As this is a brown field site, we expect significant reduction in surface water runoff.
R10 - Brentwood railway station car park St James Road, Brentwood
The wastewater network capacity in this area may be unable to support the demand anticipated from this development. Local upgrades to the existing drainage infrastructure may be required to ensure sufficient capacity is brought forward ahead of the development. Where there is a potential wastewater network capacity constraint, the developer should liaise with Thames Water to determine whether a detailed drainage strategy informing what infrastructure is required, where, when and how it will be delivered is required. The detailed drainage strategy should be submitted with the planning application. A significant assets run beneath the site. We would seek protection of these assets and may require several wayleaves /easements. Drainage hierarchy to be followed in addressing surface water. As this is brown field site, we expect significant reduction in surface water runoff.
R11 - Westbury Road Car Park, Westbury Road, Brentwood
On the information available to date we do not envisage infrastructure concerns regarding wastewater network or wastewater treatment infrastructure capability in relation to this site/s. It is recommended that the Developer and the Local Planning Authority liaise with Thames Water at the earliest opportunity to advise of the developments phasing. Please contact Thames Water Development Planning, either by email Devcon.team@thameswater.co.uk tel: 02035779998 or in writing Thames Water Utilities Ltd, Maple Lodge STW, Denham Way, Rickmansworth, Hertfordshire, WD3 9SQ Drainage hierarchy to be followed in addressing surface water. As this is a
brown field site, we expect significant reduction in surface water runoff.
R12 - Land at Hunter House, Western Road, Brentwood (Reviewed Jan18)
On the information available to date we do not envisage infrastructure concerns regarding wastewater network or wastewater treatment infrastructure capability in relation to this site/s. It is recommended that the Developer and the Local Planning Authority liaise with Thames Water at the earliest opportunity to advise of the developments phasing. Please contact Thames Water Development Planning, either by email Devcon.team@thameswater.co.uk tel: 02035779998 or in writing Thames Water Utilities Ltd, Maple Lodge STW, Denham Way, Rickmansworth, Hertfordshire, WD3 9SQ Surface water to be addressed according to the Drainage hierarchy. This being a brownfield site we expect a significant reduction in surface water runoff.
R13 Chatham Way/Crown Street Car Park, Brentwood (Reviewed Jan18)
On the information available to date we do not envisage infrastructure concerns regarding wastewater network or wastewater treatment infrastructure capability in relation to this site/s. It is recommended that the Developer and the Local Planning Authority liaise with Thames Water at the earliest opportunity to advise of the developments phasing.Please contact Thames Water Development Planning, either by email Devcon.team@thameswater.co.uk tel: 02035779998 or in writing Thames Water Utilities Ltd, Maple Lodge STW, Denham Way, Rickmansworth, Hertfordshire, WD3 9SQ Drainage hierarchy to be followed in addressing surface water. As this is a brown field site, we expect significant reduction in surface water runoff.
R14 - WILLIAM HUNTER WAY, CAR
PARK SITE, BRENTWOOD
The wastewater network capacity in this area may be unable to support the demand anticipated from this development. Local upgrades to the existing drainage infrastructure may be required to ensure sufficient capacity is brought forward ahead
of the development. Where there is a potential wastewater network capacity constraint, the developer should liaise with Thames Water to determine whether a detailed drainage strategy informing what infrastructure is required, where, when and how it will be delivered is required. The detailed drainage strategy should be
submitted with the planning application. Drainage hierarchy to be followed in addressing surface water. As this is a brown field site, we expect significant reduction in surface water runoff.
R15 - Wates Way Industrial Estate,
Ongar Road, Brentwood
On the information available to date we do
not envisage infrastructure concerns
regarding water supply network or water
treatment infrastructure capacity in relation
to this site/s. It is recommended that the
Developer and the Local Planning Authority
liaise with Thames Water at the earliest
opportunity to advise of the developments
phasing. Please contact Thames Water
Development Planning, either by email
Devcon.team@thameswater.co.uk tel:
02035779998 or in writing Thames Water
Utilities Ltd, Maple Lodge STW, Denham
Way, Rickmansworth, Hertfordshire, WD3
9SQ
Drainage hierarchy to be followed in
addressing surface water. As this is a
brown field site, we expect significant
reduction in surface water runoff.
R16 & R17- Land off Doddinghurst Road, either side of A12, Brentwood
On the information available to date we do
not envisage infrastructure concerns
regarding wastewater network or
wastewater treatment infrastructure
capability in relation to this site/s. It is
recommended that the Developer and the
Local Planning Authority liaise with Thames
Water at the earliest opportunity to advise of
the developments phasing. Please contact
Thames Water Development Planning,
either by email
Devcon.team@thameswater.co.uk tel:
02035779998 or in writing Thames Water
Utilities Ltd, Maple Lodge STW, Denham
Way, Rickmansworth, Hertfordshire, WD3
9SQ
R19- Land At Priests Lane, Brentwood
On the information available to date we do
not envisage infrastructure concerns
regarding wastewater infrastructure
capability in relation to this site.
Please note that the above comments
relate to the sewerage network within the
Thames Water supply area only. It is
recommended that Anglian Water are also
consulted for their comments in relation to
this development proposal. Drainage
hierarchy to be followed in addressing
surface water.
R23 - Brizes Corner Field, Blackmore
Road, Kelvedon Hatch
On the information available to date we do
not envisage infrastructure concerns
regarding wastewater infrastructure
capability in relation to this site.
Drainage hierarchy to be followed in
addressing surface water. Please note that
the above comments relate to the sewerage
network within the Thames Water supply
area only. It is recommended that Anglian
Water are also consulted for their
comments in relation to this development
proposal.
R24 - Land off Stocks Lane, Kelvedon Hatch
On the information available to date we do
not envisage infrastructure concerns
regarding wastewater infrastructure
capability in relation to this site.
Drainage hierarchy to be followed in
addressing surface water. Please note that
the above comments relate to the sewerage
network within the Thames Water supply
area only. It is recommended that Anglian
Water are also consulted for their
comments in relation to this development
proposal.

POLICY SP04
In relation to wastewater infrastructure it will be essential that new development is aligned with any
necessary upgrades required to ensure that the development would not overload the existing
sewerage network. Thames Water therefore support the content of Policy NE2 parts D and E and
encourage developers proposing developments to engage with them at an early stage to discuss the
wastewater infrastructure requirements for development.
The proposed policy ensures that the Local Plan is consistent with Paragraphs 20 and 41 of the NPPF.
Alongside the proposed amended text for Policy SP04, the policy will help ensure the effective
delivery of any sewerage network reinforcement works necessary to support development.

POLICY SP04
In relation to wastewater infrastructure it will be essential that new development is aligned with any
necessary upgrades required to ensure that the development would not overload the existing
sewerage network.
Thames Water support the policy in principle. However, it should be noted that new sewerage
infrastructure is delivered by the sewerage undertaker and funded through the infrastructure charge
for new developments connecting to the sewerage network. It is not therefore possible for any
necessary upgrades to be secured through CIL or S106 contributions. In order to ensure that any
necessary sewerage infrastructure reinforcement works required to support a development are
delivered ahead of the occupation of development it may be necessary for planning conditions to be
used to ensure that a development or phase of development is not occupied until the required
upgrade has been delivered. To help ensure this Policy SP04 should make reference to the use of
planning conditions as a mechanism to ensure the delivery of infrastructure alongside S106
agreements and CIL.

To address the above concern Part B of Policy SP04 could be amended to incorporate the following
wording:
"c. off-site capacity improvement works (secured through appropriate planning conditions or
agreements)"
The proposed change would ensure that planning conditions can be used to secure infrastructure
improvements necessary to support development alongside S106 agreements and CIL thereby
ensuring that the policy is effective and the Local Plan is sound.

POLICY SP01:
Thames Water support the aim of Policy SP01 (D) in relation to ensuring development does not result
in unacceptable impacts on amenity. However, as worded the policy would only be effective in
ensuring that development itself has no unacceptable impact on amenity. Consideration is also
required to be given to whether the location of proposed development is appropriate taking into
account existing sources of noise, odour and vibration to ensure that the amenity of future occupiers
of development will not be adversely affected by such issues. Where development would be affected
by an existing source of noise, odour or vibration development should only be allowed where it is
demonstrated that suitable mitigation measures can be put in place and it has been demonstrated
how these will be delivered. This would be required in order to ensure that the policy is consistent
with Paragraph 182 of the NPPF 2019.
To address the above concern it is considered that Part D(e) of Policy SP01 could be revised to read as
follows:
"e. has no unacceptable effect on health, the environment or amenity due to the release of pollutants
(such as light, noise pollution, vibration, odour, smoke, ash, dust and grit) to land, water or air, and
where the amenity of future occupiers would not be adversely impacted by existing sources of such
pollutants unless suitable mitigation measures are proposed and secured;"
The additional wording would ensure that development is not located where the amenity of future
residents would be affected by existing sources of polluntants unless suitable mitigation is provided.
This would ensure that the policy is effective and consistent with the NPPF and therefore sound.

Attachments:

Support

Brentwood Local Plan 2016 - 2033 (Pre-Submission, Regulation 19)

Representation ID: 23271

Received: 21/03/2019

Respondent: Mid and South Essex STP

Representation Summary:

Anticipated mitigation as a result of development on this site should include contribution towards increasing capacity by means of extension, reconfiguration or refurbishment or/and recruitment costs.

Full text:

1.0 Introduction
1.0.1 Thank you for consulting the Basildon & Brentwood Clinical Commissioning Group (CCG) and the Mid and South Essex Sustainability and Transformation Partnership (STP) on the above emerging Local Development Plan (LP) Document.
1.1 In reviewing the context, content and recommendations of the LP Document and its current phase of progression, the following comments are with regard to the Healthcare provision on behalf of the STP
2.0 Existing Healthcare Position in the Emerging Plan Area
2.1 The LP Document covers the administrative area of Brentwood.
2.2 Currently, within the administrative area, healthcare provision incorporates a total of 9 GP Practices, 13 pharmacists, 9 dental surgeries, 10 Opticians, 2 community clinics and 2 community hospitals.
2.3 These are the healthcare services available that this Local Plan must take into account in formulating future strategies.

Attachments:

Support

Brentwood Local Plan 2016 - 2033 (Pre-Submission, Regulation 19)

Representation ID: 24308

Received: 19/03/2019

Respondent: Strutt & Parker LLP

Agent: Strutt & Parker LLP

Representation Summary:

The proposed allocation of Land off Stocks Lane as Policy R24 and its removal from the Green Belt is considered sound and is fully supported. It has been established through the evidence base supporting the PSLP that Kelvedon Hatch is a sustainable location to accommodate a modest amount of new houses to contribute to the Borough's housing needs. Indeed, as recognised by para 68 of the NPPF and as a medium sized site, such sites make an important contribution to "meeting the housing requirement of an area and are often built out quickly". We do however have some concerns with the amount of development set out at A of the Policy and the indicative yield at page 340 and the suggested trajectory for the site at Appendix 1. These matters are dealt with below. Supporting these representations is a Vision Document at Appendix A, a review of Green Belt and Landscape Sensitivity at Appendix B and a Summary Drainage and Utility Appraisal at Appendix C. These all confirm that the development at the site is both justified and fully deliverable within the terms of para 67a) of the NPPF. Part A of Policy R24 suggests that there be provision for around 30 new homes on the site. Part A Policy HP03 of the PSLP requires proposals to take a design led approach to density to ensure schemes are sympathetic to local character and make efficient use of land. Part B expects development to achieve a net density of at least 35dph unless the special character of the surrounding area suggests that such densities would be inappropriate. The suggested amount of 30 homes set out for Policy R24 does not currently reflect these requirements or provide an accurate representation of what is achievable on site. 30 homes represent 18.6dph which clearly does not represent an efficient or effective use of the land contrary to the objectives of HP03 and the supporting text set out at 6.18 to 6.20 and 6.22. The Vision Document confirms that around 45 homes can actually be provided on the site representing a far more efficient and effective dwelling yield. 45 homes would represent a density of approximately 28dph. Whilst this does not achieve 35dph, the Vision Document demonstrates that full account has been taken of the objectives of HP03 to ensure that a scheme would be sympathetic to local character. Critically, the illustrative scheme shows provision for open space within the site to meet the objectives of Policies HP13 and BE22. These policies provide for functional on-site open space. As such, achieving a greater density would be problematical.

Change suggested by respondent:

Policy R24A - substitute 30 new homes with 45 new homes; Page R24 - indicative dwelling yield substitute 30 with 45. At para 9.195 the PSLP suggests the development would take its access from Blackmore Road. This is an error. The paragraph should be amended to refer to Stocks Lane. The site is within the control of Stonebond Properties, a local house builder with considerable experience in the development of medium sized sites, quick delivery and achieving high design and layout standards. Upon removal from the Green Belt and grant of a planning permission, it would be expected that development at the site could commence 2020/21 and be completed within two years of the Plan. As a consequence, it is recommended that the Local Development Plan Housing Trajectory at Appendix 1 is amended to provide for the following based on an increased number of homes as set out in these representations: Year 5 - 2020/21 = 10; Year 6 - 2021/22 = 35.

Full text:

These representations are submitted by Strutt & Parker on behalf of Stonebond Properties Ltd. in relation to the Brentwood Borough Council (BBC) Proposed Submission Local Plan (Regulation 19) (PSLP), and in particular with regards to our client's land interests at Stocks Lane, Kelvedon Hatch. This is proposed for allocation under Policy R24 of the PSLP. Plans showing the site are included within the Vision Document at Appendix A to this representation. As the Council will be aware, representations have previously been made on behalf of the landowner, W H Norris & Sons, in respect of the land at Stocks Lane, most recently as part of the Regulation 18 Local Plan Consultation in March 2018. Since then the site has come into the control of Stonebond Properties Ltd, a local housing developer with considerable experience of bringing forward high quality homes on small and medium sites. As a result of the previous representations and discussions with officers at Brentwood Borough Council alongside the Local Plan process, this site and land at Blackmore Road (Site R23, Brize's Corner Field, also now under Stonebond Properties' control) have been proposed as sites for future residential development within PSLP. Stonebond's overall position is one of firm support for the PSLP and this is expressed where relevant in these representations, albeit with some overarching concerns, notably in relation to certain elements of the Policy R24 in relation to the amount of development, the expected time for delivery in the Plan period and certain elements of the PSLP's Development Management Policies. Where such concerns are raised, specific changes to the relevant policies are sought and these are indicated in the following representations in order to assist in BBC making the Plan more robust and improving its soundness in terms of being positively prepared, effective, justified and consistent with national policy. Stonebond Properties request the right for its professional advisors to provide further responses on any matters appropriate to their land interests at the relevant sessions of the Examination of the submitted Local Plan. Settlement Hierarchy: Kelvedon Hatch is confirmed as a Category 3 Larger Village as set out in the Settlement Hierarchy shown at figure 2.3 of PSLP. It states that these villages are characterised by the amount of amenities and services able to cater for residents' day to day needs. Kelvedon Hatch has a local centre with a range of services, facilities, access to public transport, and education services. The PSLP sets out that Category 3 settlements should seek to make the most of brownfield redevelopment opportunities, while limited urban extensions will be encouraged to meet local needs where appropriate. The population is stated as 2,124, making Kelvedon Hatch the second largest Category 3 Settlement behind Doddinghurst. Due to the proximity of Doddinghurst (around 1km to the east), there is a reciprocal relationship between the two villages in terms of the availability and access to services and other facilities. As a result, development at Kelvedon Hatch is clearly a sustainable location to which a proportion of the Borough's housing need should be directed. In addition, as an established community, it is important that the Local Plan provides for the growth of the settlement to ensure the vitality of the community is sustained or enhanced. In line with Paragraph 78 of the NPPF, growth in one village may have the added benefit of further supporting opportunities and growth in nearby surrounding villages. The two sites for additional housing in Kelvedon Hatch identified in the PSLP at Land at Stocks Lane (R24) and west at Blackmore Road (R23) are fully supported. The proposed allocation of these two sites is considered to be justified, consistent with national policy and necessary to ensure the sustainable growth of Kelvedon Hatch and the Borough for reasons set out elsewhere in these representations. Spatial Strategy - Vision and Strategic Objectives: Vision for the Borough: The Vision for the Borough set out at Section 3 of the PSLP is supported. For the reasons set out in these representations, carefully planned development at Kelvedon Hatch as provided for at Policies R23 and R24 will make an important contribution to BBC's housing needs to meet the Local Plan objectives. Indeed, these representations and those relating to R24 make the case that a modest and justified increase in the sites' ability to accommodate more homes will assist meet those aims and provide for greater flexibility in meeting housing needs. Stonebond Properties have undertaken detailed site assessments. These confirm that there are no barriers to delivery of development. As a consequence, the expressed objectives of development in the Vision to be landscape-led responding to a "design and build with nature approach firmly embedding high quality green infrastructure through public realm to create a seamless transition to our surrounding countryside" can all be achieved and delivered in the allocation of sites R23 and R24. This is demonstrated in the accompanying Vision Documents to this representation for R24. Managing Growth - Policy SP02: Managing Growth: Policy SP02 proposes a total of 7,752 dwellings be provided in the Borough between 2011 and 2033 with 310 homes per year to 2022/23 and then 584 per year from 2022/23 taking forward a "stepped delivery" approach to deal with a projected shortfall in the first 5 years of the PSLP. This is mainly because a greater proportion of homes to be delivered in the PSLP comprise sites located in the Green Belt, resulting in longer lead in times to delivery. Whilst we do not raise objections in principle to the stepped approach as far as our clients are concerned there is a prospect that some sites in the Green Belt have the prospect of coming forward earlier, particularly smaller and medium sized developments. This certainly includes this site R24, and R23 that is the subject of a separate representation. This matter is dealt with further at Section 8 below. Furthermore, and notwithstanding the stepped approach proposed, there are still issues with BBC's over-optimistic estimates and assumptions on the delivery of larger strategic sites proposed for allocation in the PSLP. BBC are effectively placing most of its "eggs in one basket." in the range of sites that are proposed in the PSLP. It is important to note that, of the new allocations, 4,578 homes are made up of strategic allocations (of which 2,700 are at Dunton Hills Garden Village and are to be delivered in the Plan period) and 1,510 are other allocations The strategic sites therefore represent 68% of the total number of new homes of which some 59% are allocated at Dunton Hills. The ability of larger strategic sites to come forward quickly has been the subject of recent assessments in the Independent Review of Build Out, the Letwin Review (2018); and issues with their complexity, have been ably set out in the Lichfield's study From Start to Finish (2016). Both provide empirical evidence that the early delivery of such sites can be problematical due to a range of factors, including establishing required infrastructure requirements and the timing of housing delivery associated with those requirements, as well as the prolonged or protracted nature of the planning process. The Lichfield's report confirms that the planning process takes, on average, 2.5 years for the planning application determination period for up to 500 units; this can double for sites over 1,000 units. Two of the strategic sites within the PSLP's allocations also comprise developed sites currently in employment uses. The strategic sites are expected to deliver some 1555 homes within 5 years of an assumed adoption in 2020/21. Given the issues set out above it is considered that this is unrealistic and it would not be justified or the most appropriate strategy to rely on these sites for short term housing delivery. It therefore emphasises the need to review the ability of smaller or medium sized sites such as R23 and R24 to provide for greater flexibility and more homes which have a far greater prospect for short term delivery to ensure the Local Plan is sound. Sequential Land Use: Paragraph 4.22 and 4.23 of the PSLP suggested that a sequential approach is to be taken to the determination of planning applications, referring only to prioritising brownfield land in urban areas and brownfield land in the Green Belt. The reasons for this are unclear when the PSLP strategy includes releasing land from the Green Belt to meet development needs which includes the sites the subject of these representations. The growth requirements set out by Policy SP02, and the sequential approach to meeting those requirements are referred to at paragraph 3.23, provide for the justification for the chosen spatial strategy. As a consequence, it is not justified to suggest that a sequential test be taken for the determination of planning applications and paras 4.22 and 4.23 should be deleted from the PSLP. SP04 - Developer Contributions: There are no objections to the general approach expressed in Policy SP04 for developer contributions. However, section E is nether precise, necessary or justified and could be open to misinterpretation. It is therefore recommended that this be omitted. Resilient Built Environment: We are generally supportive of the Council's objectives to achieve a resilient built environment. Nevertheless, there are concerns that the policies set out in the PSLP and as drafted may have an impact on viability, deliverability and affordability for housing development generally. We are aware of the representations made by the House Builders Federation (HBF) referring to sustainable construction (BE020), allotments (BE20), Green and Blue Infrastructure (BE18), access to nature (BE19), digital infrastructure (BE10), open space (BE22), electrical vehicle charging (BE15), housing quality (HP06). The implications of the requirements set out do not appear to have been fully considered as part of the viability assessment. As a consequence, we would suggest that the viability assessment for the PSLP is revisited to reflect on these requirements to better inform or provide clarity on the proposed policies. Policy BE01 - Future Proofing: Whilst the Council's objectives towards future proofing of development are broadly supported, it is questionable whether it is necessary to set out a detailed planning policy to this effect when a number of the criteria set out comprise a series of aspirations. It is of some concern that Part A of the Policy requires that all applications must take into account....... when the process of development management and determination of applications is far more prescriptive and binary in decision making. As a consequence, it is suggested that Policy BE01 should be set out as supporting text rather than a specific policy. Policy BE02 - Sustainable Construction and Resource Efficiency: Whilst the Council's objectives towards sustainable construction and resource efficiency are broadly supported, it is questionable whether it is necessary to set out a detailed planning policy to this effect when a number of the criteria set out comprise a series of aspirations. The requirement to submit details of measures that increase resilience to the threat of climate change at b. is also considered to be over prescriptive when such techniques may vary substantially. The general principles set out at para 5.19 are reflective of the fact that these matters ought more properly to be dealt with by supporting text rather than a specific policy. In addition, we are aware of comments made by the HBF on this policy and we support those comments. Policy BE20 - Allotments and Community Food Growing Space: Whilst the Council's aspirations for providing allotments are acknowledged, the policy as set out provides for no clear thresholds as to when such space should be provided which is not justified in the terms set out. On this basis, it is recommended that the policy should either be omitted and dealt with by the text to the PSLP or justified against thresholds or site specific requirements. In this respect, it may be that large strategic sites may need to include a requirement but it is certainly not necessary for smaller or medium sized sites, such as those the subject of these representations. Policy BE22 - Open Space in New Development: The policy is broadly supported. As can be seen from the Vision document that accompanies these representations, our proposed scheme for R24 makes provision for such space. It is nevertheless questionable whether it is necessary for all open space to be fully equipped (D.). The need for equipped space should also be related to the amount of development proposed and/or availability or local equipped areas. As a consequence, it is recommended that criteria D is amended to be refined to provide clarity on when equipped open space is required eg. on sites over 50 homes. Housing Provision: Policy HP01 - Housing Mix: The Council's approach to providing for an appropriate mix of dwelling types is generally supported. However, the Policy as set out refers to the Borough wide requirements in the Strategic Housing Market Assessment (SHMA) and does not necessarily take into account a local area or sub area within the Borough. It is important to note that the SHMA requirements, at Figure 6.1, confirms that it is an indicative mix guide for market housing. It is also noted that para 6.5 confirms that the final mix will be subject to negotiation. This is welcomed on the basis that some flexibility will be necessary in certain circumstances as part of the planning application process. As a consequence, it is suggested that para 6.5 should provide greater clarity and a minor change confirming that the final mix will be subject to negotiation "as part of a planning application" rather than "with the applicant". We are aware of the representations submitted by HBF regarding accessible homes and justification. We support those views. It is questionable whether it is necessary for the PSLP to set out in planning policy the requirements of Building Regulations. Policy HP03 - Residential Density: We support the PSLP's approach to residential density as set out in Policy HP03. This is considered to be justified based on the evidence and consistent with the national policy. As far as our client's land interests are concerned at R23 and R24, both sites are capable of providing an increased density to that expressed for the relevant policies R23 and R24. However, part B of the policy quite properly acknowledges that a chosen density should take into account the character of the surrounding area and other site constraints. This is supported. A further explanation of suggested density or yield for R24 is set out at Section 8 below. Policy HP05 - Affordable Housing: We note that the SHMA provides justification for the affordable housing requirements. However, it is questionable whether the precise tenure/mix should be set out at B(a) of the Policy, given that requirements can change relatively quickly over time and the prescriptive approach may not take into account precise local needs. As a consequence, it is recommended that the criteria under B(a) should omit the reference to 86% and 14% proportions. It is suggested, in the alternative, that "the mix, size, type and cost of affordable homes will meet the identified housing needs of the Council's area and local needs as appropriate, established by housing need assessments including the SHMA". Design and Place-making: The approach set out in the PSLP for design and place-making is broadly supported. However, we note that there are effectively seven policies (HP12 - HP18) which provide the requirements against these matters. We also note that there are some areas of repetition on some of the objectives against those policies. We consider that those commenting on and determining applications should preferably have one or two identified policies to refer to and/or applicable thresholds to more succinctly set out requirements. This would ensure that planning applications can be more effectively judged against context, design and place-shaping criteria. Natural Environment: We generally support the Council's approach to Green Belt and the identification of suitable sites to meet the Council's housing and other needs. Accompanying these representations is an overview of the Green Belt and Landscape Sensitivity considerations relating to Stonebond's land interests at R23 and R24 to confirm the suitability of removing those sites from the Green Belt and limited impact on the landscape. Policy NE13 - Site Allocations in the Green Belt: We welcome the PSLP's intentions to remove sites R23 and R24 from the Green Belt. This calls into question the need for Policy NE13. The requirements set out by criterion A and B are dealt with by other policies in the Plan. If there are site specific requirements relating to sites, these should be covered within the specific policies relating to those sites. Site Allocations: Policy R24 - Land off Stocks Lane: The proposed allocation of Land off Stocks Lane as Policy R24 and its removal from the Green Belt is considered sound and is fully supported. It has been established through the evidence base supporting the PSLP that Kelvedon Hatch is a sustainable location to accommodate a modest amount of new houses to contribute to the Borough's housing needs. Indeed, as recognised by para 68 of the NPPF and as a medium sized site, such sites make an important contribution to "meeting the housing requirement of an area and are often built out quickly". We do however have some concerns with the amount of development set out at A of the Policy and the indicative yield at page 340 and the suggested trajectory for the site at Appendix 1. These matters are dealt with below. Supporting these representations is a Vision Document at Appendix A, a review of Green Belt and Landscape Sensitivity at Appendix B and a Summary Drainage and Utility Appraisal at Appendix C. These all confirm that the development at the site is both justified and fully deliverable within the terms of para 67a) of the NPPF. The Vision Document demonstrates that careful consideration has been given to the emerging policies set out at BE01, BE08, BE22, as well as those relating to Design and Place-making at HP12, HP13, HP14, HP15 and HP18 of the PSLP to confirm that a scheme can meet the PSLP objectives in this regard. The Summary Drainage and Utility Appraisal at Appendix B confirms that there are no constraints to delivery. In addition, Stonebond Properties commissioned a transport appraisal from Ardent Consulting Engineers. This has confirmed that the location of the access shown in the Vision Document meets normal highway requirements in terms of safety and visability. This has been confirmed in speed surveys undertaken in Stocks Lane. The Green Belt and Landscape Sensitivity Assessment at Appendix B confirms that the release of the site from the Green Belt is justified. It also confirms that there would be no significant impact on the surrounding landscape. Part A of Policy R24 suggests that there be provision for around 30 new homes on the site. Part A Policy HP03 of the PSLP requires proposals to take a design led approach to density to ensure schemes are sympathetic to local character and make efficient use of land. Part B expects development to achieve a net density of at least 35dph unless the special character of the surrounding area suggests that such densities would be inappropriate. The suggested amount of 30 homes set out for Policy R24 does not currently reflect these requirements or provide an accurate representation of what is achievable on site. 30 homes represent 18.6dph which clearly does not represent an efficient or effective use of the land contrary to the objectives of HP03 and the supporting text set out at 6.18 to 6.20 and 6.22. The Vision Document confirms that around 45 homes can actually be provided on the site representing a far more efficient and effective dwelling yield. 45 homes would represent a density of approximately 28dph. Whilst this does not achieve 35dph, the Vision Document demonstrates that full account has been taken of the objectives of HP03 to ensure that a scheme would be sympathetic to local character. Critically, the illustrative scheme shows provision for open space within the site to meet the objectives of Policies HP13 and BE22. These policies provide for functional on-site open space. As such, achieving a greater density would be problematical. In addition, it is important to note that the site is on the edge of the settlement where there is a need for sensitivity, having regard to the countryside to the east and south. Para 6.22 of the PSLP confirms that efficient land use is critical to the delivery of this Plan for the reasons set out at Sections 4 and 6 above against this background, it is recommended that amendments are made as follows: Policy R24A - substitute 30 new homes with 45 new homes; Page R24 - indicative dwelling yield substitute 30 with 45. At para 9.195 the PSLP suggests the development would take its access from Blackmore Road. This is an error. The paragraph should be amended to refer to Stocks Lane. The site is within the control of Stonebond Properties, a local house builder with considerable experience in the development of medium sized sites, quick delivery and achieving high design and layout standards. Upon removal from the Green Belt and grant of a planning permission, it would be expected that development at the site could commence 2020/21 and be completed within two years of the Plan. As a consequence, it is recommended that the Local Development Plan Housing Trajectory at Appendix 1 is amended to provide for the following based on an increased number of homes as set out in these representations: Year 5 - 2020/21 = 10; Year 6 - 2021/22 = 35. These comments on Policy R24 provide greater certainty on delivery of the site. In addition, the changes suggested would contribute to the issues we have identified elsewhere with the PSLP specifically in relation to the supply and delivery of homes generally. As a result, we trust that the Council will be able to agree modifications/changes accordingly.

Object

Brentwood Local Plan 2016 - 2033 (Pre-Submission, Regulation 19)

Representation ID: 26037

Received: 12/03/2019

Respondent: Ms Elaine Harris

Legally compliant? Not specified

Sound? No

Duty to co-operate? Not specified

Representation Summary:

I consider the proposal to build numerous houses within our small beautiful village appalling! We recently moved to the village and do not wish this wonderful place to change. I object to building on green belt land. The village is prone to flooding and thus development will increase the risk. Our small community does not have the infrastructure to cope with all the additional people these homes would contain. The local primary school is already full. The roads congested. The doctors surgery oversubscribed. Children play out, I feel additional traffic and access to the site would result in an accident.

Change suggested by respondent:

I do not consider any modification can be made. The proposal should be cancelled, there are more suitable sites where houses could be built.

Full text:

I consider the proposal to build numerous houses within our small beautiful village appalling! We recently moved to the village and do not wish this wonderful place to change. I object to building on green belt land. The village is prone to flooding and thus development will increase the risk. Our small community does not have the infrastructure to cope with all the additional people these homes would contain. The local primary school is already full. The roads congested. The doctors surgery oversubscribed. Children play out, I feel additional traffic and access to the site would result in an accident.

Attachments: