Thames Water will work with developers and local authorities to ensure that any necessary infrastructure reinforcement is delivered ahead of the occupation of development. Where there are infrastructure constraints, it is important not to underestimate the time required to deliver necessary infrastructure. For example: to understand, design and deliver local network upgrades can take around 18 months and Sewage Treatment & Water Treatment Works upgrades can take 3-5 years. Implementing new technologies and the construction of a major treatment works extension or new treatment works could take up to 10 years.