9.175

Showing comments and forms 1 to 2 of 2

Object

Brentwood Local Plan 2016 - 2033 (Pre-Submission, Regulation 19)

Representation ID: 22219

Received: 05/03/2019

Respondent: Mr Robin Ibrahim

Legally compliant? No

Sound? No

Duty to co-operate? No

Representation Summary:

With flawed evidence, in particular transport impact, more education and health infrastructure is needed, site location unsuitable.

Change suggested by respondent:

Remove site R19 from plan

Full text:

The evidence base is flawed:
The transport Assessment is inaccurate as it has excluded traffic along Priests Lane, and was taken at times which excluded a large proportion of school traffic, despite Council assurances that a traffic assessment would be done for Priests Lane.
The Transport Assessment does not account for the increased usage of Priests Lane from the proposed development of 1000 houses in Shenfield travelling to the A127, nor does it account for the impact of the Elizabeth Line.
The Plan fails to address safety of residents : the technical submissions residents that new road accesses along Priests Lane are hazardous have not been addressed, nor concerns that the road design is dangerous for increased traffic movements.
The site does not meet relevant sustainability conditions, notably access, transport network, mitigation of impact on local services, and unacceptable effect on health due to increased pollution.
The Priests Lane sites have been rejected previously because the land was deemed a valuable open urban space.
No account has been made of the increased pollution along Middleton Hall Lane and Priests Lane, the junction of which is a pollution hotspot.
The Lane was never meant to be a main distributary road which it has now become. Residents have pointed out that as such it does not comply with the Essex Design Guide with respect to road and pavement width.
Local Plans should address not only housing but traffic concerns, health care and education needs.
The sustainability review refers to traffic as a concern, but no mitigation options have been identified.
No specific or robust argument has been made that a viable access point is possible.
When considered against reasonable alternatives these sites cannot be deemed justified and there is nowhere in the plan which allows for the enhancement of infrastructure as a result of development.
There is no additional provision for increased educational and health needs, the expansion of Hogarth School is to meet current demands and there is already a low level of GPs per head. Schools further afield which may have space will require a car journey to attend, exacerbating the already dire traffic situation.

Object

Brentwood Local Plan 2016 - 2033 (Pre-Submission, Regulation 19)

Representation ID: 22476

Received: 18/03/2019

Respondent: Essex County Council

Legally compliant? Yes

Sound? No

Duty to co-operate? Yes

Representation Summary:

2. Justified.

Endeavour School is a special school for children aged 5 years to 16 years with moderate learning difficulties and complex needs and is the only special school in Brentwood. ECC welcomes the proposed creation of 6th form provision at Endeavour school and intends to commission some of the places for local children with an Education Health and Care Plan. The 6th form provision will enable local children to continue their education within their community and reduce travel time to specialist establishments elsewhere.

This should be reflected in paragraph 9.175.

Change suggested by respondent:

Amend paragraph 9.175 as follows -
The Endeavour School is a Special Educational Needs school which adjoins the site to the south is seeking to expand to accommodate a 6th form. ECC welcomes this proposal and intends to commission some of the places for local children with an Education Health and Care Plan. The 6th form provision will enable local children to continue their education within their community and reduce travel time to specialist establishments elsewhere. The school....'

Full text:

2. Justified.

Endeavour School is a special school for children aged 5 years to 16 years with moderate learning difficulties and complex needs and is the only special school in Brentwood. ECC welcomes the proposed creation of 6th form provision at Endeavour school and intends to commission some of the places for local children with an Education Health and Care Plan. The 6th form provision will enable local children to continue their education within their community and reduce travel time to specialist establishments elsewhere.

This should be reflected in paragraph 9.175.